MEP to IP1 delay

Dear All,

I am aware of the AOR -> NA1 - > MEP -> IP1 -> NA2 -> IP2 -> PPR cycle

My application timeline is as follows

AOR - Jan 9 NA1 - Jan 9 MEP - Feb 1

I have been tracking my application once a day and there has not been any change in the BG. it shows NA just like it did before MEP. There was no email about update nor any time when I checked when the BG showed ‘In Progress’ or IP1. So I am of the impression that my Status is NA1 only. is this NA1 or NA2?

Has this happened for anybody else? Usually I have heard that IP1 will be in the next 1-2 days from MEP. But it has been 7 days since MEP but the BG check is the same NA. Any advice?

Regards